District 3 Construction Projects
Live webcam of State School BB-1 in Sunny Isles Beach.
Enter Password only: PW: region2
 

Sunny Isles Beach Community School:
Milestone Schedule Highlights for 90 day look-ahead commencing
January 21, 2008 through April 10, 2008

  • February 1, 2008:         Pour concrete slab on grade in Building 1 (A/B)
  • February 2, 2008:         Complete erection of concrete tilt panels for Building E
  • February 4, 2008:         Start interior paint in Building 1 (A/B)
  • February 4, 2008:         Start drywall installation in Building C
  • February 6, 2008:         Pour concrete slab at second floor in Building E
  • February 8, 2008:         Start placing roof steel joist in Building E
  • February 9, 2008:         Pour concrete slab on grade in Building C
  • February 11, 2008:       Start ceiling grid in Building 1 (A/B)
  • February 11, 2008:       Start ceramic tile in Building 1 (A/B)
  • February 18, 2008:       Start installation of mill work (cabinets) Building 1 (A/B)
  • February 25, 2008:       Start ceramic tile in Building C
  • February 25, 2008:       Start erection of parking structure (Building D)
  • February 28, 2008:       Start drywall installation in Building E
  • March 1, 2008:            Start roofing of Building E
  • March 3, 2008:            Start installation of mill work (cabinets) Building C
  • March 4, 2008:            Start interior paint in Building C
  • March 4, 2008:            Installation of main electrical switch gear in Building E
  • March 7, 2008:            Installation of chillers in Building E
  • March 17, 2008:          Pour concrete slab on grade in Building D
  • March 24, 2008:          Start vinyl composition tile installation in Building 1(A/B)
  • April 7, 2008:               Start framing of interior partitions in Building D

Note:         Building 1 (A/B):       Classrooms, Art and Music Suites
                  Building C:                Classrooms and Administrative Suite
                  Building D:                Parking Garage
                  Building E:                Cafetorium and Media Center

 

 

Miami Beach Sr High Replacement:
The first phase of construction, (Classrooms, Media Center, Fine Arts and Auditorium), is scheduled for occupancy for January 2008. Phase II of the project which includes the new gymnasium, cafeteria, and full renovation of the administration and science buildings is projected for completion in December 2009.

 

Aventura Waterways K-8 Center:
The new prototype K-8 school, with a capacity of 1642 student stations, is under construction and on schedule to open in August 2008. This school will relieve Virginia Boone/Highland Oaks Elementary, Madie Ives Elementary, and Highland Oaks Middle.

 

Broad/Bay Harbor El Addition:
This project will provide 551 student stations for the K-8 conversion including a new music suite and dining facility; it is currently under construction and on schedule to open in August 2008. The concurrent construction of the Sunny Isles Beach K-8 will significantly relieve the existing overcrowding at this school. An Interlocal Agreement with the Town of Bay Harbor will provide parking for the school while preserving the open green space and facility use by the residents.

 

SS – QQQ1 (FIU/Biscayne Landings):

 
Start Date
Finish Date

Actual Construction Begins                                              3-Dec-07                             
Substantial Completion                                                                                   7-Aug-09

Earthwork & Site Clearing Begins                                     3-Dec-07

Begin foundations for Classroom building                         11-Feb-08
Structural Steel for Classroom Building                             5-May-08            7-Aug-08
Classroom Building Complete                                                                        30-Apr-09

Begin Foundations for Gym Building                                  25-Feb-08
Structural Steel for Gym                                                    11-Nov-08           2-Dec-08
Gym Complete                                                                                                4-Aug-09

Begin foundations for Admin Building                                5-Mar-08
Structural Steel for Admin Building                                    1-Aug-08             10-Nov-08
Admin Building Complete                                                                                  7-Aug-09

Begin Foundations Cafetorium Bldg                                   11-Feb-08
Structural Steel Cafetorium Bldg                                        26-Jun-08             31-Jul-08
Cafetorium complete                                                                                         7-Aug-09

 

Note:  This reflects a 20-month construction duration. 
We are currently looking at ways to shorten this time.


 

Southside Elementary Addition:
The planned expansion and partial renovation of this historically significant school in the Brickell area is currently in the design phase and planned for construction in the 2008-2009 fiscal year. The projected completion of this 826 student station facility will be during the 2009-2010 school year.

 

 